Installation & Commissioning of all Refrigeration, Electrical and Data Cabling elements of the project

Background

Project value: £540,000

Programme: 20 weeks

In autumn 2011, Technical Retail Services Limited (TRS) were awarded the Refrigeration Installation contract at the M&S Westfield Stratford City Shopping Centre.

This sizeable project formed part of the prestigious Stratford Olympic Games Development located in the area.

TRS was responsible for the installation and commissioning of all Refrigeration, Electrical and Data cabling elements of the project.

Project overview

Through careful planning and design the Refrigeration plant and cabinets were successfully installed using a hydrocarbon primary system utilising R290 refrigerant and a secondary system utilising a CO2 pumped system.

Outcome

Through meticulous project management and a high quality of installation, the project was completed on-time and within budget.